Road Repair Progress in Seribu Islands Reaches 40 Percent

Road repair is conducted in Untung Jawa, Tidung, and Lancang Islands. Its progress has reached 40 Percents and it is targeted to finish in December.

Several locations are in repairing progress. We target it to finish in December

South of Seribu Islands Sub-district Head, Agus Setiawan explained that three locations as long as 5,400 square meters will be repaired with total budget Rp 2,585 billion.

"Current progress reaches 40 percent," he said, Tuesday (11/28).

Road at Cilincing Bridge Needs Repair

He mentioned, con-block will be used for the repaired roads. Currently, personnel conducts concrete cansteen installation with sand in several locations.

"Several locations are in repairing progress. We target it to finish in December," he affirmed.   

Linked News
Popular News indeks
  1. Survivors of Collapsed Houses in Malaka Jaya Receive Social Assistance

    access_time30-01-2025 remove_red_eye2209 personNurito
  2. Logistics Aid for Jakarta Flood Victims Keeps Being Distributed

    access_time30-01-2025 remove_red_eye984 personAldi Geri Lumban Tobing
  3. City Council Chairman Supports City Government Optimizing Assistance for Rorotan Farmers

    access_time30-01-2025 remove_red_eye678 personDessy Suciati
  4. N. Jakarta Vice Mayor Distributes Assistance to Flood Survivors in Sukapura

    access_time30-01-2025 remove_red_eye481 personAnita Karyati
  5. Rain Brings Excitement to Rawa Belong Milkfish Festival 2025

    access_time28-01-2025 remove_red_eye452 personFolmer